Which G98 form you need depends on what you’re connecting. For a compliant plug-in solar kit, since 27 August 2026 the householder notifies, using G98’s new Form B2 or its online equivalent, ENA’s registration site myplugin.solar. For a permanently wired system, the installer completes Form B1, which most operators still call Form B. Either way it’s a notification after commissioning, not an application, and it goes to your network operator, not your electricity supplier.
Until August there was only Form B, written for a qualified installer, with an installer signature block a plug-in owner couldn’t complete. Engineering Recommendation G98 Issue 2 Amendment 1 2026 fixed that for plug-in kits: “For Plug-in Micro-generator(s), the Customer may take the role of Installer.” Two parts are still catching up. The final wording of Form B2 sits behind a login, so the detail below comes from the June 2026 consultation draft. And the network operators’ side isn’t live: none of them offers a Form B2 download yet, and the screens they’ll use to respond to plug-in registrations are listed by ENA as upcoming.
The G98 application process
Strictly it’s a notification, not an application: for small-scale generation under 16 A per phase, around 3.68 kW, G98 is fit and notify. People still call it a G98 application or a DNO application, and the process is the same whichever name you use. The only true application in G98 is Form A, for several installations in one area.
For a plug-in solar kit
- Check the kit is Compliant. Find the exact model on our register tracker. myplugin.solar only lets you choose devices on its approved list.
- Check for existing solar. If the property already has panels, ask your network operator in writing before you plug in. ENA’s site and the G98 text don’t say the same thing about this (see G98 or G99 below).
- Register at myplugin.solar. Verify your email with a one-time code, enter your postcode and address, choose your device and submit. ENA says it will “send your notification automatically” to your network operator.
- Keep a record. Screenshot the confirmation and keep any email. It’s your evidence that you notified.
Our myplugin.solar report covers the one-device rule, what to do if your kit isn’t listed and the DNO-side caveat in more detail.
For a permanently wired installation
- Find your DNO. It’s set by your postcode area, not your electricity supplier: National Grid Electricity Distribution, SSEN, UK Power Networks, Northern Powergrid, Electricity North West or SP Energy Networks. Our DNO lookup finds it from a postcode or the distributor ID on your bill.
- Gather the details. Manufacturer, model, the ENA Type Test Register reference and the inverter’s rated output in kW.
- Commission, then complete Form B1. Most operators take it as an online form or by email; the route for each is further down this page.
- Send it within the deadline, which is 28 days of commissioning for most operators and 30 for SP Energy Networks.
- Keep the acknowledgement. It’s what a Smart Export Guarantee supplier will ask for as proof of connection if you apply for export payments.
What G98 is, and what it is not
Engineering Recommendation G98 is the document that governs how small generating equipment connects to the low-voltage distribution network in Great Britain. The current issue is Engineering Recommendation G98 Issue 2 Amendment 1 2026. It’s published by the Energy Networks Association and sits as an annex to the Distribution Code, which is why network operators describe notifying under it as a legal obligation rather than a courtesy. Our G98 guide covers the standard itself, the protection settings and G98 vs G99.
It covers generation up to 16 A per phase, around 3.68 kW on a single-phase supply. A compliant plug-in solar device tops out at 800 VA of apparent power and 3.5 A of output current, so it sits a long way inside that ceiling.
One point of scope, because it’s routinely got wrong: G98 is a Great Britain document. Northern Ireland uses G98/NI, and the Interim Product Specification says that applying the specification there is subject to further consideration. If you’re in Northern Ireland, nothing on this page is your process.
Notification is mandatory, and the plug-in route now exists
Forms A, B1, B2, C, D1 and D2
Amendment 1 split the old Form B and Form D in two. Most people only ever need one form.
- Form B2 is the installation document for a plug-in kit, completed by the customer. If you have a plug-in kit, this is your form, and myplugin.solar is the online way to submit it.
- Form B1 (the old Form B) is the installation document for a wired system at a single premises, completed by the installer.
- Form A is an application where micro-generators are being connected at more than one premises in the same area within a short window. It’s a network-planning form, not a household one.
- Form C is the type test verification report. Manufacturers complete it, not you.
- Form D2 tells the operator a plug-in kit has been permanently removed, and Form D1 (the old Form D) does the same for a wired unit.
The operators’ download pages haven’t caught up. On 8 October 2026 SP Energy Networks and Northern Powergrid still published the older Form A, B, C and D set, and none of the operator pages we checked offered a Form B2 or D2.
Form B2: the plug-in kit form
Form B2 is short. In the consultation draft it asks for:
- Your name, address, postcode, phone, email and MPAN
- The kit’s location within your installation
- The manufacturer and the energy source code (“for PV Micro-generator, this would be R11”)
- The manufacturer’s reference number, which is the ENA Type Test Register system reference
- Registered capacity in kW, storage capacity in kWh, and the phase
Then a customer declaration, signed and dated, that:
“the information provided in this Installation Document is accurate to the best of my knowledge; no more than one Plug-in Micro-generator is connected in the Customer’s Installation stated above; and where there are other Micro-generators in the Customer’s Installation, the aggregate Registered Capacity … does not exceed 16 A per phase.”
There’s no installer block, no isolation switch, no schematic and no cut-out photograph. Amendment 1 exempts plug-in kits from those parts of G98. The draft form also says: “As an alternative for completing this form, a Customer connecting a Plug-in Micro-generator may use the connect and notify process through the Connect Direct platform.” That’s what myplugin.solar is: Connect Direct’s DNO screen counts a plug-in submission as complete “when a consumer registers their Plug-in Solar device on the myplugin.solar website”.
Two caveats on Form B2
The wording is from the draft. The published G98 Amendment 1 forms are free on the ENA document catalogue but need a login to order. Ofgem says changes after consultation were “limited to clarifications, simplified customer facing forms, implementation arrangements and minor editorial amendments”, so the final Form B2 may ask for less than the list above.
The operators’ side isn’t live. ENA lists the Connect Direct release that lets DNOs “view, filter and respond to consumer Plug-in Solar notifications, and assign an export MPAN” (version 3.3.0) as upcoming, with no date. The operators’ own pages still describe installer routes and don’t mention plug-in solar. UK Power Networks says “Only installers can notify us on behalf of customers.” Those pages are about wired systems. For a plug-in kit, register on myplugin.solar and keep your own record.
What to gather before you start
For myplugin.solar: an email address you can get a code at, your postcode, and the kit’s manufacturer and model exactly as printed on it, because the site searches by “manufacturer, model or device name”.
For Form B1, have all of this to hand and the form takes about fifteen minutes:
- Your full address and postcode
- Your MPAN, from your electricity bill
- The make and model of the equipment, exactly as printed on it
- The inverter’s AC output rating, in kW
- The commissioning date
- The equipment’s entry on the ENA Type Test Register
- The installer’s details and accreditation
- A system schematic
Form B1, box by box
Form B1 is the form for a permanently wired system, and the one most operators still publish as Form B. It contains an Installer Details block (installer, Accreditation / Qualification, address, contact, phone, email and installer signature), and the declaration at the foot is headed “Declaration: to be completed by Installer for Micro-generators Tested to EREC G98”. We downloaded and read the copies published by National Grid Electricity Distribution and SSEN and confirmed both are the same ENA template. That’s why a plug-in owner shouldn’t use it: the installer block is for a person a plug-in kit doesn’t have, and Form B2 exists to replace it.
Steps 1 to 3 and 5 to 6 below apply to Form B2 as well, because both forms ask for the same device details.
Step 1: Get the exact product details
Take these from the device, not from the listing. You want the product name and the model number printed on the microinverter or the device label: the exact product, not the range it belongs to. Marketplace listings routinely describe a kit by a family name that appears nowhere on the hardware, and the rating shown in a listing photograph isn’t evidence of anything.
Step 2: Find your DNO
Your distribution network operator owns the cables in your street. It isn’t the company that bills you. There are six operators across fourteen licence areas in Great Britain, and you can find yours by postcode at energynetworks.org, or faster, from your MPAN.
Step 3: Find your MPAN
Your MPAN is the long number on your electricity bill, usually printed in a bordered grid and labelled Supply Number. The first two digits are the distributor ID, and they tell you which network operator you belong to without you having to guess from a map.
| First two digits | Licence area | Operator |
|---|---|---|
| 10 | Eastern England | UK Power Networks |
| 11 | East Midlands | National Grid Electricity Distribution |
| 12 | London | UK Power Networks |
| 13 | Cheshire, Merseyside and Northern Wales | SP Energy Networks |
| 14 | West Midlands | National Grid Electricity Distribution |
| 15 | North Eastern England | Northern Powergrid |
| 16 | North Western England | Electricity North West |
| 17 | Northern Scotland | SSEN |
| 18 | Southern Scotland | SP Energy Networks |
| 19 | South Eastern England | UK Power Networks |
| 20 | Southern England | SSEN |
| 21 | Southern Wales | National Grid Electricity Distribution |
| 22 | South Western England | National Grid Electricity Distribution |
| 23 | Yorkshire | Northern Powergrid |
Source: the Energy Networks Association’s network operator directory, checked 10 August 2026. The postcode checker at energynetworks.org gives the same answer if you’d rather not dig out a bill.
Step 4: Fill in the customer, installer and site details
Customer Details. Your name, address, contact person if different, telephone, email, and a Customer signature. If you rent, this is still you: the notification records what is connected at the supply, and it doesn’t go to your landlord.
Installer Details. Installer, Accreditation / Qualification, address, contact, and installer signature. Your installer fills these in.
MPAN(s). As above. If your bill shows two MPANs, use the import one. An export MPAN is a separate thing that your supplier arranges later, and only if you’re pursuing an export tariff.
Location within Customer’s Installation. Where the generation sits in the property.
Location of Lockable Isolation Switch. G98 is written around an isolator that can be locked in the off position, and wired systems have one. Plug-in kits are exempt from this section under Amendment 1, which is one reason Form B2 has no such box.
Energy source and energy conversion technology. Not a word: a code. The form says “enter codes from tables 1 and 2 below”, and the tables are printed on the form itself. The B2 draft gives the PV code as R11. Read yours off the version you’re using rather than trusting a number quoted elsewhere.
Step 5: Enter the registered capacity
This is the box that catches everyone. It’s the inverter’s rated AC output, not the panel wattage. Electricity North West puts it plainly in its own guidance: where the installation includes an inverter, the rating is taken to be the inverter’s continuous steady state rating.
So a kit with 1,000 W of panels feeding an 800 VA microinverter is an 0.8 kW installation for this purpose. Under the Interim Product Specification a compliant device can’t exceed 800 VA, which means every compliant plug-in solar device in Great Britain writes 0.8 kW or less in this box. If you’ve written 2 kW because that’s what the panels add up to, you’ve answered a different question.
Which phase column. On Form B1 there’s no “number of phases” box. The capacity table has 3-Phase and Single Phase columns headed PH1, PH2 and PH3, and the form instructs: “Use PH 1 column for single phase supply.” A compliant plug-in device is single phase only, so on either form its figure goes against a single phase.
The capacity box in one line
Step 6: Enter the energy storage capacity
Zero, on the versions that ask. The field is “Energy storage capacity for Electricity Storage devices (kWh)”, and battery storage within the device is not permitted under the plug-in route, so a compliant plug-in device has nothing to declare.
Not every operator publishes the same vintage of the form. Electricity North West’s published Form B is an older issue that has no energy storage field at all, so if the box isn’t there, nothing is wrong: you have a different version. Check the footer of the form you downloaded.
Step 7: Add the manufacturer reference number, and read the declaration
The reference number is the equipment’s entry on the ENA Type Test Register. The form says as much: “this number should be registered on the ENA Type Test Register as the system reference”. More on that below.
Then read the installer’s declaration at the foot, which is narrower than people expect:
“I declare that the relevant Micro-generators and the installation which together form a Micro-generating Plant within the scope of EREC G98 at the above address, conform to the requirements of EREC G98. This declaration of compliance is confined to Micro-generating Plant tested to EREC G98 or EREC G83 as applicable at the time of commissioning. I enclose a copy of the system schematic which has been left on site at the Customer’s incoming meter location.”
Two things follow. First, the declaration references EREC G98 and G83 only. BS 7671 doesn’t appear anywhere on Form B1, so anything you’ve read about the form asking you to certify compliance with the Wiring Regulations is wrong. Second, a system schematic is a universal requirement on Form B1: every copy asks the installer to enclose one and leave a copy at the incoming meter location.
Connect Direct and the cut-out photograph
The ENA Type Test Register reference and what you may find there
The register is at connect-direct.energynetworks.org. Filter by device type and look for the exact model of the complete kit, not the microinverter inside it. A register entry can cover a component rather than the assembled product, which lets a seller point at a real register entry while the kit you’re buying has never been assessed as a whole. Connect Direct now says it doesn’t accept “registrations for inverter-only products under the plug-in solar category”, but check what the entry covers.
As at 13 November 2026, the register had 164 records under the Plug-in Solar device type, 145 of them Compliant. Our certified kits tracker carries the current state, entry by entry. Only Compliant devices can be chosen on myplugin.solar.
Non-compliant sounds harsher than it is. ENA’s published taxonomy puts “Non-compliant” as a sub-category of Further Information Required, the parent status meaning that following review of the device and its documentation, more is needed before a compliant status can be achieved. The sub-status reads that the device and documentation can’t be deemed compliant at this stage, and that once the comments have been actioned and the documentation updated by the manufacturer, it will be reviewed again in due course.
So it’s a staging state that anticipates another look, not a failure and not a safety finding. What it does mean for you today is simple: a device at that status isn’t compliant yet and can’t be relied on. The register moves weekly, so check the date on anything you read about it, including this page.
Registration is not verification
Where to send it
For a plug-in kit, there’s one place: myplugin.solar, which sends the notification to whichever network operator serves your address.
For a wired installation, there’s no single national inbox. Each of the six network operators in Great Britain has its own route. SP Energy Networks wants the form within 30 days rather than 28, and asks to hear from you before you commission rather than after. Northern Powergrid puts an account registration in front of its online form. UK Power Networks routes notification through a portal only approved installers may use. We’ve checked all six on their own websites:
- SSEN: Form B by email, with different addresses for Scotland and England
- UK Power Networks: Smart Connect, restricted to approved installers
- National Grid Electricity Distribution: an online form needing no account, or Form B by email or post
- Northern Powergrid: an online service request behind an open account login, or Form B by email
- Electricity North West: email only, to a named G98 mailbox, on an older version of the form
- SP Energy Networks: Form B within 30 days, with an SSEG test report attached
After you send it
Keep a copy of what you sent and of anything that comes back. For a wired system the acknowledgement is the document a supplier may ask for if you apply for an export tariff, and National Grid Electricity Distribution runs a request service if you need an acceptance letter you don’t have. For a plug-in kit, don’t expect a reply yet: the operators can’t respond to myplugin.solar registrations until ENA releases the DNO side, so your own record is the evidence.
On timescales, we’d rather be dull than wrong. Turnaround figures circulate freely in forums and range from a few hours to several weeks. Some operators publish a submission deadline for you and no response standard for themselves. Ask your own operator what it expects.
Telling them when you take it down
The specification requires products to carry deregistration guidance alongside the registration guidance, so the duty runs both ways. G98 now has Form D2 for a plug-in kit that has been “permanently removed from use”, and Form D1 for a wired unit. myplugin.solar covers replacing a kit (register the new one) and moving house (register again at the new address), but not permanent removal, and no operator offers a Form D2 download yet. If you take a kit down for good, email your operator with the address, the device and the date, and keep the reply. Our moving house guide covers the other case.
G98 or G99?
G99 applies above 16 A per phase. A plug-in device is 3.5 A at most. On its own it’s G98, however many panels the listing photograph shows.
The related trap is arithmetic. If G98 covers 3.68 kW, and a device is 800 VA, it’s tempting to conclude you may connect four of them. You may not. IPS version 2 permits one device per final circuit, but its own note records that Engineering Recommendation G98 Issue 2 Amendment 1 2026 restricts this to one device per household, and G98 itself now says one plug-in kit per Customer Installation. Two limits, and the tighter one wins: one device per household.
Existing solar is where the sources differ. G98’s text allows a plug-in kit alongside wired generation if the total stays within 16 A per phase. ENA’s registration site says that with an existing 3.68 kW G98 system “you must use a qualified installer to apply for G99 approval. Any additional generation must be wired in and not a plug-in installation.” If you already have panels, ask your operator in writing before you plug in.
Frequently asked questions
Which G98 form do I need for plug-in solar?
Form B2, the plug-in installation document added by G98 Issue 2 Amendment 1, or its online equivalent, ENA's registration site myplugin.solar. No network operator offers a Form B2 download yet, so in practice you register on myplugin.solar.
What is the difference between G98 Form B1 and Form B2?
Form B1 is the old Form B, for permanently wired systems. It has an installer block, a lockable isolation switch field and a schematic declaration. Form B2 is for a single plug-in kit, is completed by the customer and has none of those. The customer declares that no more than one plug-in kit is connected and that any other generation keeps the total within 16 A per phase.
What are the steps involved in the G98 process?
For a plug-in kit: check it's Compliant on the ENA register, then register on myplugin.solar by verifying your email, confirming your address, choosing your device and submitting. For a wired system: the installer commissions it, completes Form B1 with the register reference and sends it to the network operator within 28 days.
Do I need a qualified electrician to sign anything off?
Not for a compliant plug-in kit. G98 Amendment 1 says the customer may take the role of installer for a plug-in micro-generator, and Form B2 carries a customer declaration rather than an installer one. Separately, the specification requires manufacturers to advise professional assessment above 960 W of panels, but the advice is mandatory rather than the assessment, and a kit above 960 W is fully compliant.
What does a G98 certificate look like?
G98 has no document by that name. People mean one of three things: the manufacturer's Form C type test report, the product's entry on the ENA Type Test Register, or the network operator's acknowledgement or acceptance letter. For a plug-in kit, keep the register reference and your record of the registration.
How do I get my G98 certificate?
By notifying and keeping what comes back. For a plug-in kit, keep a record of your myplugin.solar submission, because network operators can't yet respond to those notifications. For a wired system, keep the operator's acknowledgement; National Grid Electricity Distribution runs a request service if your supplier asks for an acceptance letter you don't have.
Do I use the solar panel wattage or the inverter wattage on the G98 form?
The inverter. For a compliant plug-in solar device that is 800 VA or less, whatever the panels add up to.
Do we need to register both the batteries and the solar inverter?
If your kit has a battery in it, it isn't on the plug-in route at all. Battery storage within the device isn't permitted, so a compliant plug-in device has no storage to declare. Battery-integrated systems can be installed conventionally, by an electrician, who notifies on Form B1.
Does G98 approval mean I can plug solar into any UK socket?
No. The specification permits connection to socket circuits only, not lighting circuits or circuits feeding fixed equipment, and prohibits extension cables and extension leads, multi-way adaptors, RCD adaptors, travel adaptors and plug convertors. There are also surfaces on which installation isn't permitted at all.
What is the G98 letter?
Another name for the network operator's acknowledgement or acceptance letter. There's no standard format, which is why it goes by several names.
For the standard itself, see our G98 guide. To check where the register has got to, see our tracker of certified plug-in solar kits. And if your kit has a battery in it, start with what the battery rules exclude.